What is LOD (Level of Development) in BIM? Meaning and Levels Explained

By , Founder of ZYSNOR · Updated · Checked · 5 min read

In simple words

Level of Development (LOD) tells you how complete and reliable an element in a BIM model is, so others know how far they can trust it. The common scale runs LOD 100, 200, 300, 350, 400 and 500.

The levels are set out in the BIMForum LOD Specification, which builds on the American Institute of Architects (AIA) definitions and is updated regularly.

How it works

LOD is set element by element, not for a whole model. A BIM execution plan states which LOD each element must reach at each stage, and who is responsible for it. A model at "LOD 300" is shorthand: some elements may be higher, others lower, as the plan allows. LOD covers both the geometry and the information attached to it.

The scale for one door

Table of a door at LOD 100, 200, 300, 350, 400 and 500
Each level adds reliability, not just more detail.
  • LOD 100: a symbol or placeholder says a door will be there; cost may come from an area rate.
  • LOD 200: a generic door with approximate size, shape and position.
  • LOD 300: a specific door with the right size, shape and location; quantities can be measured from it.
  • LOD 350: as 300, plus how it meets the wall, frame fixings and other systems.
  • LOD 400: detailed enough to make and install.
  • LOD 500: checked on site as built. BIMForum has not defined this level in its specification, since it concerns field verification rather than development.

LOD across a project

LOD rising from 100 at concept to 400 at fabrication
The BIM execution plan sets the target LOD for each element and stage.

Level of development and level of detail

Level of detail describes how much is drawn; level of development describes how far the element and its data can be relied on. A beautifully detailed door can still be LOD 200 if its size is only a guess.

Worked example: the measurable share of a tender model

A tender model has 1,200 elements. The QS will measure from the model only elements at LOD 300 or above.

Bar chart: 840 elements at LOD 300 and above, 300 at LOD 200, 60 at LOD 100
70% of the elements can be measured from the model; the rest need allowances.
  • Total: 840 + 300 + 60 = 1,200 elements
  • Measurable share: 840 / 1,200 × 100 = 70%
  • The other 300 + 60 = 360 elements (30%) are priced from provisional quantities, allowances or rates per m².

Step by step: using LOD on a project

  1. Agree which edition of the LOD specification the project follows.
  2. Build an element table: each element type, the LOD needed at each stage and the author.
  3. Write it into the BIM execution plan and the appointments.
  4. Check models at each stage against the table, element by element.
  5. Tell users, such as the QS, which elements are reliable enough for their task.

Common mistakes

  • Confusing level of development with level of detail.
  • Asking for LOD 400 everywhere, which costs time without benefit.
  • Stating one LOD for a whole model instead of per element.
  • Measuring quantities from LOD 100 or 200 elements as if they were final.
  • Not saying which edition of the specification applies.

Related terms

Frequently asked questions

Is LOD the same as level of detail?

No. Detail is about how much is drawn; development is about how reliable the element and its information are.

Which LOD do I need for a quantity takeoff?

Generally LOD 300 or higher for the measured elements.