Glossary · CAD and BIM
What is Clash Detection in BIM? Types, Example and How It Works
In simple words
Clash detection is the BIM check that finds places where elements from different models run into each other, such as a duct passing through a beam, before anything is built. Fixing a clash on screen is far cheaper than on site.
Each discipline's model is checked against the others. Every conflict found is a clash, reviewed by the team and fixed in the design model, not on site.
How it works
The architectural, structural and MEP models are combined (federated) in a coordination tool such as Navisworks Manage, whose Clash Detective runs the tests. A test compares one selection against another, for example all ducts against all beams, using a test type and a tolerance. Revit also has a simpler Interference Check for hard clashes between selected categories.
Test types
- Hard: the two objects intersect.
- Hard (conservative): also reports items that may intersect, so fewer real clashes are missed.
- Clearance: the objects come closer than a set gap, for example space for insulation, access or maintenance.
- Duplicates: the same object placed twice in the same place.
Tolerance
The tolerance is a small distance below which clashes are ignored. Without one, tiny touches between pipes and their fittings can flood the report; with one too large, real clashes are hidden.
Clash statuses
In Navisworks, a clash found for the first time is New. One found in an earlier run and still there is Active. The team can mark clashes Reviewed or Approved (accepted as they are). A clash from an earlier run that is no longer found is Resolved; if it comes back, it becomes New again.
Worked example: a clearance test
The MEP model is tested against the structure with a 25 mm clearance. The top of a duct sits 15 mm below a beam.
- Required gap: 25 mm
- Actual gap: 15 mm
- Shortfall: 25 − 15 = 10 mm, so the duct is reported and must drop by at least 10 mm, or the beam or insulation be changed.
After the second run of the same test, the results are:
- Total: 120 + 45 + 20 + 10 + 85 = 280 clashes
- Resolved share: 85 / 280 × 100 = 30.4%
- Still open (new and active): 120 + 45 = 165
Step by step: running a clash test
- Make sure all models share the same coordinates and units.
- Federate them in the coordination tool.
- Set up tests by discipline pair (MEP against structure, MEP against architecture) with a type and tolerance.
- Run the tests, then group related clashes, for example all clashes along one duct run.
- Assign each group to the person who will fix it, with a due date.
- Fix in the design models, update the federated model and run the tests again.
Common mistakes
- Tests that are too wide, giving thousands of results nobody reviews; filter and group them.
- No tolerance, or one too large.
- Models on different coordinates or units, so everything clashes or nothing does.
- Approving clashes to make the report look clean without a reason recorded.
- Checking only hard clashes and forgetting the clearance needed for insulation and maintenance.
Related terms
- CAD and BIMGlossary term
Building Information Modeling (BIM)
Building Information Modeling (BIM) is a way of designing, building and running a building with one shared digital model. The model holds the 3D shape and the information about every element, such as type, material, size and cost.1 min read · Added 20 Nov 2026 - CAD and BIMGlossary term
IFC (Industry Foundation Classes)
IFC (Industry Foundation Classes) is an open, vendor-neutral data standard for describing buildings and infrastructure, so models can be shared between different BIM software. It is developed by buildingSMART International and published as ISO 16739-1. Files usually have the extension .ifc.1 min read · Added 20 Nov 2026 - CAD and BIMGlossary term
Level of Development (LOD)
Level of Development (LOD) tells you how complete and reliable an element in a BIM model is, so others know how far they can trust it. The common scale runs LOD 100, 200, 300, 350, 400 and 500.2 min read · Added 20 Nov 2026 - Construction and QSGlossary term
Variation order
A variation order is a formal instruction, usually from the engineer or architect, that changes the work in a construction contract, such as adding, omitting or changing work. It adjusts the contract price and sometimes the time.2 min read · Added 20 Nov 2026
Frequently asked questions
Which software does clash detection?
Navisworks Manage (Clash Detective) is common; other BIM coordination tools do it too.
What is a clash tolerance?
A small distance below which clashes are ignored, to remove meaningless results.