What is Quantity Takeoff (QTO)? Meaning, Example and How It Works
In simple words
Quantity takeoff (QTO, also "taking off") is the process of measuring quantities, such as areas, lengths, volumes and counts, from drawings, models and specifications, mainly to work out construction cost. The word "takeoff" is also used for the list of quantities the process produces. Quantity surveyors and estimators do it.
Why it matters
The client's estimate, the contractor's tender and the site's material orders all rest on the same quantities. A complete, checked and traceable takeoff makes tenders comparable and later variations easy to value; a careless one is carried straight into the price and creates claims.
Types
- Count (nr): doors, windows, sockets and sanitary fittings.
- Length (m): skirting, pipes, kerbs and handrails.
- Area (m²): plaster, paint, tiles and blockwork.
- Volume (m³): concrete, excavation and fill.
- Manual or digital: on dimension paper, on screen from PDF or CAD drawings, or extracted from a 3D BIM model. The tool changes; the measurement rules and the need to check do not.
Worked example
One room in a Lahore house: 5.00 m × 4.00 m, wall height 3.00 m, one door 0.90 × 2.10 m and one window 1.50 × 1.20 m.
| Item | Working | Quantity |
|---|---|---|
| Floor area | 5.00 × 4.00 | 20.00 m² |
| Perimeter | 2 × (5.00 + 4.00) | 18.00 m |
| Gross wall area | 18.00 × 3.00 | 54.00 m² |
| Openings | 1.89 + 1.80 | 3.69 m² |
| Net wall area | 54.00 − 3.69 | 50.31 m² |
| Skirting | 18.00 − 0.90 (door) | 17.10 m |
| Doors, windows | counted | 1 nr each |
Both openings are over 1.00 m², so they are deducted under the usual finishes rule; small openings may be kept, depending on the method of measurement the contract names.
Common mistakes
- Measuring to the wrong face of a wall, or double counting at corners.
- Forgetting to deduct openings, or deducting openings the rules say to keep.
- Using the wrong drawing scale or an old revision.
- Mixing units, such as m² against m.
- Trusting model quantities without checking how the model was built.
Related terms
- Construction and QSGlossary term
Bill of Quantities (BOQ)
A Bill of Quantities (BOQ) is a document that lists every item of work in a construction project with a description, a unit and a measured quantity, so every contractor prices the same work.5 min read · Added 20 Nov 2026 - Construction and QSGlossary term
Gross area and net area
Gross area is the full area of a surface before anything is taken out; net area is what is left after deducting the openings and voids that the measurement rules say to deduct.5 min read · Added 20 Nov 2026 - Construction and QSGlossary term
Opening deductions
Opening deductions are the measurement rules that say which doors, windows and voids are taken out of a measured quantity and which small openings are left in.5 min read · Added 20 Nov 2026 - Construction and QSGlossary term
Running metre (linear metre)
A running metre (also called a linear metre, written m, Rm or RMT) is a length measured along an item, whatever its width or height. Items such as skirting, cornice, handrail, pipes and kerbs are measured and priced per running metre.5 min read · Added 20 Nov 2026 - Construction and QSGlossary term
Wall finishing area (plaster and paint)
Wall finishing area is the area of wall surface that receives plaster, paint, tiles or another finish. It is the wall perimeter times the finish height, minus the openings that the measurement rules say to deduct.4 min read · Added 20 Nov 2026
Frequently asked questions
Can BIM do the takeoff automatically?
A model can produce quantities directly, but they are only as good as the model; they still need checking against the measurement rules.
What is the difference between a material takeoff and a quantity takeoff?
A material takeoff lists raw materials (bags of cement, blocks); a quantity takeoff lists measured work items (m² of blockwork).
What happens to the takeoff after measuring?
The quantities are grouped into items and collated into a bill of quantities that contractors price.