What is a Bill of Quantities (BOQ)? Meaning, Example and How It Works

By , Founder of ZYSNOR · Updated · Checked · 5 min read

In simple words

A Bill of Quantities (BOQ) is a document that lists every item of work in a construction project with a description, a unit and a measured quantity. Contractors price each line, so every bidder prices exactly the same work. It is usually prepared by a quantity surveyor from the drawings and the specification, before the project goes to tender.

Five boxes joined by arrows: drawings, take-off, BOQ, pricing and contract
The client fixes the quantities; contractors only add their rates.

Why it matters

A BOQ makes tenders comparable, gives the client a firm basis for the contract price and becomes the reference for valuing variations and interim payments. When a wall is added or removed during construction, the agreed rate for that item is used to value the change.

Types

  • Firm BOQ: quantities are measured from a complete design, and the contract price is fixed unless the design changes.
  • Approximate BOQ: used when the design is not complete; the work is re-measured as it is built and paid at the tendered rates.

How a BOQ is organised

  • Preliminaries: site set-up, supervision, insurance, temporary works and other costs that are not part of one building element.
  • Measured work, in bills: usually one bill per trade or element (substructure, concrete, masonry, finishes, doors, MEP). Each line has an item code, a description, a unit, a quantity and empty Rate and Amount columns.
  • Provisional sums and prime cost sums: allowances for work that cannot be measured yet, for example a sum for specialist lighting.
  • Collection and summary: each bill total is carried to a summary page that gives the tender total.

Measurement rules

The quantities follow a published method of measurement so that everyone reads them the same way: NRM2 in the UK (it replaced SMM7 in 2013), POMI for many international projects and CESMM4 for civil engineering work. The rules say, for example, which openings are deducted from wall areas and in which unit each item is measured.

Worked example

One masonry bill for a villa in Riyadh, priced in SAR:

A masonry bill with three priced items and a total of 15,928.00
One BOQ page: each amount is quantity times rate, and the page total goes to the summary.
  • B-01: 120 m² × 45.00 = 5,400.00
  • B-02: 64 m² × 38.00 = 2,432.00
  • B-03: 368 m² × 22.00 = 8,096.00
  • Bill 2 total: 5,400.00 + 2,432.00 + 8,096.00 = 15,928.00
Bar chart of four BOQ summary lines adding up to 48,278.00 SAR
The summary adds every bill and the provisional sums: 48,278.00 SAR in this example.

Step by step: making a simple BOQ

  1. List the items from the drawings and the specification, trade by trade.
  2. Measure each item in the unit the rules require (m, m², m³, nr or item).
  3. Write a clear description: material, size, location and finish.
  4. Add provisional sums for work that cannot be measured yet.
  5. Group the items into bills, add a summary page and have another person check the quantities.

Common mistakes

  • Mixing units, such as m² in one line and m in the next for the same work.
  • Deducting openings differently from the stated measurement rules.
  • Vague descriptions that two contractors read differently.
  • Forgetting preliminaries and provisional sums.
  • Copying quantities from an old project without re-measuring.

Related terms

Frequently asked questions

Who prepares a BOQ?

Usually a quantity surveyor or cost consultant, from the drawings and specifications.

Is a BOQ the same as a quantity takeoff?

No. The takeoff is the measuring; the BOQ is the organised, described and priced list that results from it.

Which rules are used to measure a BOQ?

A method of measurement agreed for the project, for example RICS NRM2 in the UK or POMI in parts of the Middle East.