What is Rate Analysis? Meaning, Example and How It Works

By , Founder of ZYSNOR · Updated · Checked · 3 min read

In simple words

Rate analysis is working out the price of one unit of a construction item, such as 1 m³ of concrete or 1 m² of plaster, by adding up the materials, labour and equipment it needs, then adding overheads and profit. Contractors' estimators and clients' quantity surveyors prepare it.

Why it matters

Every rate in a priced BOQ is the result of a small calculation. Rate analysis shows that calculation, so a client can spot a tender rate that is too low to be realistic, and a contractor can price a new item fairly in a variation when no existing rate fits.

Types

The parts of a rate:

  • Materials: quantity per unit plus wastage, times the delivered price.
  • Labour: hours of each trade per unit (the output rate) times its hourly cost.
  • Plant and equipment: hire, fuel or running cost spread over the output, plus small tools.
  • Overheads and profit: a percentage added to the direct cost. Official schedules such as the CPWD analysis of rates give basic rates exclusive of the contractor's profit and overheads, which are added separately.
Five boxes joined by arrows: item, materials, labour, plant and add-ons
A unit rate is built from its resources and then the overheads and profit are added.

Worked example

1 m² of 200 mm blockwork (illustrative SAR prices, not current market rates).

Rate build-up for 1 m² of 200 mm blockwork (illustrative)
Resource Working Cost (SAR)
Blocks 1 ÷ (0.40 × 0.20) = 12.50; × 1.04 waste = 13.00 × 3.00 39.00
Mortar 0.02 m³ × 300.00 6.00
Mason 0.80 h × 12.00 9.60
Labourer 0.80 h × 8.00 6.40
Small plant and tools item 1.00
Direct cost 39.00 + 6.00 + 9.60 + 6.40 + 1.00 62.00
Overheads and profit 15% 62.00 × 0.15 9.30
Rate per m² 62.00 + 9.30 71.30

Materials are the largest part: 45.00 of 71.30. A real analysis uses current local prices, measured outputs and the wastage the specification allows.

Bar chart: materials 45.00, labour 16.00, plant 1.00, overheads and profit 9.30, rate 71.30
Materials are the largest part of this rate: 45.00 of 71.30.

Common mistakes

  • Forgetting wastage or carriage to site.
  • Using old material prices.
  • Adding overheads twice, in the rate and again in the preliminaries.
  • Copying a rate from another city or year without checking it.

Related terms

Frequently asked questions

Is rate analysis the same as a schedule of rates?

No. A schedule of rates lists finished rates; rate analysis shows how each rate is built up.

Who prepares it?

Usually the contractor's estimator or the client's quantity surveyor.

Does ZYSNOR publish material rates?

Yes. The ZYSNOR rates pages show official monthly material rates for Pakistan (PBS) and Saudi Arabia (GASTAT), with the source and date.