Glossary · Construction and QS
What is a Provisional Sum? Meaning, Example and How It Works
In simple words
A provisional sum is an amount of money put in a tender or BOQ for work that cannot be fully described or priced yet. When the work is done, the sum is taken out and replaced by the value of the work actually carried out. It is usually estimated by the client's cost consultant or quantity surveyor.
Why it matters
A provisional sum lets a tender go out before every detail is designed. A few sums keep the project on time; too many leave the final cost uncertain, because a large share of the contract sum is still a guess when the contract is signed.
Types
- Defined provisional sum: described in enough detail (nature of the work, how it is fixed, scope and limits) that the contractor is expected to allow for it in the programme, planning and preliminaries.
- Undefined provisional sum: less well described, so the contractor cannot be expected to allow for it, and the client usually carries the time and cost risk. NRM suggests that a sum without the required information is treated as undefined, whatever it is called.
- Not the same as a prime cost sum: money for work or materials from a subcontractor or supplier nominated by the client.
Worked example
A BOQ for a villa in Riyadh has two provisional sums (illustrative figures).
| Provisional sum | Sum in BOQ | Final value | Change |
|---|---|---|---|
| Kitchen fittings | SAR 50,000 | SAR 46,500 | 46,500 − 50,000 = −3,500 |
| Signage | SAR 12,000 | SAR 13,800 | 13,800 − 12,000 = +1,800 |
| Net change | −3,500 + 1,800 = −1,700 |
The contract sum falls by SAR 1,700. Each sum is omitted and the valued work is added in its place.
How a provisional sum is settled, step by step:
- The BOQ includes the sum, for example "Provide the sum of SAR 50,000 for kitchen fittings".
- When the design is ready, the architect or engineer instructs the work.
- The work is valued under the contract's valuation rules.
- The provisional sum is omitted and the value of the work is added.
Common mistakes
- Using a provisional sum where the work could be measured.
- Calling a sum "defined" without the required description.
- Confusing it with a provisional quantity, a prime cost sum or a contingency.
- Forgetting that the final value can be higher than the sum.
Related terms
- Construction and QSGlossary term
Bill of Quantities (BOQ)
A Bill of Quantities (BOQ) is a document that lists every item of work in a construction project with a description, a unit and a measured quantity, so every contractor prices the same work.5 min read · Added 20 Nov 2026 - Construction and QSGlossary term
Variation order
A variation order is a formal instruction, usually from the engineer or architect, that changes the work in a construction contract, such as adding, omitting or changing work. It adjusts the contract price and sometimes the time.5 min read · Added 20 Nov 2026 - Construction and QSGlossary term
Rate analysis
Rate analysis is working out the price of one unit of a construction item, such as 1 m³ of concrete or 1 m² of plaster, by adding up the materials, labour and equipment it needs, then adding overheads and profit. Contractors' estimators and clients' quantity surveyors prepare it.3 min read · Added 20 Nov 2026 - Construction and QSGlossary term
Method of measurement
A method of measurement is a published set of rules for how construction work is measured and described in a BOQ, so everyone measures the same work in the same way.6 min read · Added 20 Nov 2026 - Construction and QSGlossary term
Quantity takeoff
Quantity takeoff (QTO, also "taking off") is the process of measuring quantities, such as areas, lengths, volumes and counts, from drawings, models and specifications, mainly to work out construction cost. The word "takeoff" is also used for the list of quantities the process produces. Quantity surveyors and estimators do it.3 min read · Added 20 Nov 2026
Frequently asked questions
Can the contract sum go up because of a provisional sum?
Yes. The final value of the work can be more or less than the sum.
Do all contracts use provisional sums?
No. Provisional sums do not exist in NEC4; changes are handled as compensation events.
Who decides the amount?
The client's cost consultant or quantity surveyor estimates it and writes it into the tender; contractors do not price it.