What is a Provisional Sum? Meaning, Example and How It Works

By , Founder of ZYSNOR · Updated · Checked · 3 min read

In simple words

A provisional sum is an amount of money put in a tender or BOQ for work that cannot be fully described or priced yet. When the work is done, the sum is taken out and replaced by the value of the work actually carried out. It is usually estimated by the client's cost consultant or quantity surveyor.

Why it matters

A provisional sum lets a tender go out before every detail is designed. A few sums keep the project on time; too many leave the final cost uncertain, because a large share of the contract sum is still a guess when the contract is signed.

Types

  • Defined provisional sum: described in enough detail (nature of the work, how it is fixed, scope and limits) that the contractor is expected to allow for it in the programme, planning and preliminaries.
  • Undefined provisional sum: less well described, so the contractor cannot be expected to allow for it, and the client usually carries the time and cost risk. NRM suggests that a sum without the required information is treated as undefined, whatever it is called.
  • Not the same as a prime cost sum: money for work or materials from a subcontractor or supplier nominated by the client.
Four steps: sum in the tender, instruction, valuation, adjustment
The sum is only a placeholder; the final account uses the real value.

Worked example

A BOQ for a villa in Riyadh has two provisional sums (illustrative figures).

Two provisional sums against their final values (illustrative)
Provisional sum Sum in BOQ Final value Change
Kitchen fittings SAR 50,000 SAR 46,500 46,500 − 50,000 = −3,500
Signage SAR 12,000 SAR 13,800 13,800 − 12,000 = +1,800
Net change −3,500 + 1,800 = −1,700

The contract sum falls by SAR 1,700. Each sum is omitted and the valued work is added in its place.

Bar chart of two provisional sums against their final values
One sum came in lower and one higher; only the net change affects the contract sum.

How a provisional sum is settled, step by step:

  1. The BOQ includes the sum, for example "Provide the sum of SAR 50,000 for kitchen fittings".
  2. When the design is ready, the architect or engineer instructs the work.
  3. The work is valued under the contract's valuation rules.
  4. The provisional sum is omitted and the value of the work is added.

Common mistakes

  • Using a provisional sum where the work could be measured.
  • Calling a sum "defined" without the required description.
  • Confusing it with a provisional quantity, a prime cost sum or a contingency.
  • Forgetting that the final value can be higher than the sum.

Related terms

Frequently asked questions

Can the contract sum go up because of a provisional sum?

Yes. The final value of the work can be more or less than the sum.

Do all contracts use provisional sums?

No. Provisional sums do not exist in NEC4; changes are handled as compensation events.

Who decides the amount?

The client's cost consultant or quantity surveyor estimates it and writes it into the tender; contractors do not price it.