What is Concrete Volume? Meaning, Example and How It Works

By , Founder of ZYSNOR · Updated · Checked · 5 min read

In simple words

Concrete volume is the space a concrete element fills, measured in cubic metres (m³). For a simple shape it is length × width × thickness (or depth). Quantity surveyors, site engineers and contractors use it to price, order and check concrete.

Why it matters

Concrete is priced, ordered and paid for by the cubic metre. A small error in units or a double-counted overlap changes the bill and the truck order, and ready-mix concrete that arrives short or in excess costs money and time.

Types

  • Measured (net) volume: the volume from the drawings, used in the BOQ. Under RICS NRM2, in-situ concrete is measured net, with no deduction for reinforcement, formwork, chairs or cast-in accessories.
  • Order volume: the net volume plus an allowance for waste, spillage and uneven formwork. The allowance belongs in the rate or the order, never in the measured quantity.

Formulas for common shapes

Table of volume formulas for slabs, columns, beams and round columns with examples
Convert every size to metres before you multiply.
  • Slab, wall or footing: length × width × thickness.
  • Rectangular column: breadth × depth × height.
  • Beam under a slab: length × width × (beam depth − slab thickness), so the slab part is not counted twice.
  • Round column or pile: π × r² × height. For r = 0.20 m and 3.00 m: 3.1416 × 0.04 × 3.00 = 0.377 m³.

Worked example

The frame of a small guard room in Jeddah:

  • Footings: 4 × (1.20 × 1.20 × 0.50) = 4 × 0.72 = 2.88 m³
  • Slab: 6.00 × 4.00 × 0.15 = 3.60 m³
  • Beams: 2 × (6.00 × 0.30 × (0.45 − 0.15)) = 2 × 0.54 = 1.08 m³
  • Columns: 4 × (0.30 × 0.30 × 3.00) = 4 × 0.27 = 1.08 m³
  • Measured volume: 2.88 + 3.60 + 1.08 + 1.08 = 8.64 m³
  • Order quantity with an illustrative 3% allowance set by the estimator: 8.64 × 1.03 = 8.90 m³
Bar chart of concrete volume by element: footings 2.88, slab 3.60, beams 1.08 and columns 1.08 cubic metres
The slab and footings hold most of the concrete in this frame.
Section of a slab over a beam, with only the beam part below the slab measured
0.45 m beam − 0.15 m slab = 0.30 m of beam depth to measure.

Units at a glance

Converting drawing sizes to metres and cubic metres
Size on drawing In metres Note
150 mm 0.15 m divide mm by 1,000
1 m³ 1,000 litres useful for small pours
0.15 m × 6.00 × 4.00 3.60 m³ correct
150 × 6.00 × 4.00 3,600 wrong: 1,000 times too big

Step by step

  1. List every concrete element from the drawings and convert all sizes to metres.
  2. Work out one element with its formula, then multiply by the number of identical elements.
  3. Remove overlaps so each piece of concrete is counted once.
  4. Add the elements for the measured (BOQ) volume.
  5. Add the waste allowance only when you prepare the order.

Common mistakes

  • Multiplying millimetres by metres.
  • Counting the beam through the slab depth.
  • Deducting reinforcement, which NRM2 does not deduct.
  • Adding the waste allowance to the BOQ quantity.
  • Rounding each element to one decimal before adding them up.

Related terms

Frequently asked questions

How many litres are in one cubic metre?

1 m³ = 1,000 litres.

Where do a beam and a slab overlap, which one is counted?

Count the shared part once; the method of measurement and the drawings say which element it belongs to.

Is the reinforcement volume deducted?

Usually no. NRM2, for example, does not deduct the volume of reinforcement from in-situ concrete.