What is a Bar Bending Schedule (BBS)? Meaning, Example and How It Works

By , Founder of ZYSNOR · Updated · Checked · 6 min read

In simple words

A bar bending schedule (BBS) is a table that lists every reinforcement bar in a concrete element: its mark, diameter, shape, cut length and number. It is used to cut and bend the steel and to work out its total weight for ordering and billing. It is prepared from the reinforcement drawings, usually by the detailer or the contractor's quantity surveyor, and checked before any steel is cut.

Why it matters

Steel is cut and bent off site or in a yard, so a wrong length or count is found only when the bar does not fit. A checked BBS gives the exact bars to cut, the weight to order and the weight to bill, which keeps waste and disputes down. The steel fixer bends from it, the site orders bars from it and the QS bills steel by weight from it.

Types

A BBS is usually prepared per structural element:

  • Footing and raft schedules: mostly straight bars in two directions, plus starter bars for columns.
  • Column schedules: main vertical bars and closed links.
  • Beam schedules: top and bottom bars, extra bars at supports, and links.
  • Slab schedules: main and distribution bars, often in long runs with laps.

What a BBS lists

What each column of a bar bending schedule gives
Column What it gives
Member and bar mark where the bar goes and its unique label (01, 02, 03)
Type and diameter bar grade and size in mm
Shape code a standard code for the bent shape
Number of members and bars how many members, and bars in each
Dimensions A, B, C the lengths of each leg of the shape
Cut length the length of straight bar needed before bending
Total length and mass number × cut length, then × mass per metre

Shape codes and cut length

BS 8666:2020 sets two-digit shape codes and how each dimension is measured: for example 00 is a straight bar, 11 has one 90° bend, 21 has two 90° bends and 51 is a closed link. A bar loses a little length at every bend, so use the standard's formula for each code; for a straight bar the cut length is simply A.

Line drawings of shape codes 00, 11, 21 and 51 with dimensions A, B and C
Each code fixes the shape; the schedule only adds the dimensions.

Mass of a bar

Steel weighs about 7,850 kg/m³, so 1 m of bar weighs d² × 0.006165 kg (d in mm), often rounded to d² ÷ 162. For a 12 mm bar: 144 × 0.006165 = 0.888 kg/m.

Bar chart of mass per metre for 8 to 25 mm bars, from 0.395 to 3.854 kg/m
Mass rises with the square of the diameter: a 25 mm bar weighs almost ten times an 8 mm bar per metre.

Worked example

Five identical ground beams, B1, for a house in Lahore:

A three-line BBS for beam B1 with a total of 215.56 kg
One schedule: total length first, then mass by diameter.
  • Mark 01: 5 beams × 3 bars = 15 bars × 4.80 m = 72.00 m; 72.00 × 1.579 = 113.69 kg
  • Mark 02: 5 × 2 = 10 bars × 4.80 m = 48.00 m; 48.00 × 0.888 = 42.62 kg
  • Mark 03 (links): 5 × 25 = 125 links × 1.20 m = 150.00 m; 150.00 × 0.395 = 59.25 kg
  • Total: 113.69 + 42.62 + 59.25 = 215.56 kg, or about 0.22 t

Step by step: writing a BBS

  1. Give every different bar in each member its own bar mark.
  2. Note the diameter, grade, shape code and dimensions A, B, C from the drawing.
  3. Work out the cut length with the formula for that shape code.
  4. Multiply members × bars per member × cut length, then by the mass per metre.
  5. Have a second person check marks, numbers and lengths before cutting.

Common mistakes

  • Using the drawing length instead of the cut length.
  • Mixing shape codes from different standards in one schedule.
  • Forgetting laps and starter bars.
  • Counting links for one beam but not multiplying by the number of beams.
  • Rounding the mass per metre too early in long schedules.

Related terms

Frequently asked questions

Who prepares the BBS?

Usually the structural engineer, detailer or contractor's QS from the reinforcement drawings, and it is checked before bending.

Why is the BBS in kilograms?

Reinforcement is bought and usually billed by weight, so lengths are converted to mass.

Is the d² ÷ 162 rule exact?

It is a close rounding of the exact formula based on 7,850 kg/m³; product standards list the nominal mass per metre for each size.