What is a Bar Bending Schedule (BBS)? Meaning, Example and How It Works
In simple words
A bar bending schedule (BBS) is a table that lists every reinforcement bar in a concrete element: its mark, diameter, shape, cut length and number. It is used to cut and bend the steel and to work out its total weight for ordering and billing. It is prepared from the reinforcement drawings, usually by the detailer or the contractor's quantity surveyor, and checked before any steel is cut.
Why it matters
Steel is cut and bent off site or in a yard, so a wrong length or count is found only when the bar does not fit. A checked BBS gives the exact bars to cut, the weight to order and the weight to bill, which keeps waste and disputes down. The steel fixer bends from it, the site orders bars from it and the QS bills steel by weight from it.
Types
A BBS is usually prepared per structural element:
- Footing and raft schedules: mostly straight bars in two directions, plus starter bars for columns.
- Column schedules: main vertical bars and closed links.
- Beam schedules: top and bottom bars, extra bars at supports, and links.
- Slab schedules: main and distribution bars, often in long runs with laps.
What a BBS lists
| Column | What it gives |
|---|---|
| Member and bar mark | where the bar goes and its unique label (01, 02, 03) |
| Type and diameter | bar grade and size in mm |
| Shape code | a standard code for the bent shape |
| Number of members and bars | how many members, and bars in each |
| Dimensions A, B, C | the lengths of each leg of the shape |
| Cut length | the length of straight bar needed before bending |
| Total length and mass | number × cut length, then × mass per metre |
Shape codes and cut length
BS 8666:2020 sets two-digit shape codes and how each dimension is measured: for example 00 is a straight bar, 11 has one 90° bend, 21 has two 90° bends and 51 is a closed link. A bar loses a little length at every bend, so use the standard's formula for each code; for a straight bar the cut length is simply A.
Mass of a bar
Steel weighs about 7,850 kg/m³, so 1 m of bar weighs d² × 0.006165 kg (d in mm), often rounded to d² ÷ 162. For a 12 mm bar: 144 × 0.006165 = 0.888 kg/m.
Worked example
Five identical ground beams, B1, for a house in Lahore:
- Mark 01: 5 beams × 3 bars = 15 bars × 4.80 m = 72.00 m; 72.00 × 1.579 = 113.69 kg
- Mark 02: 5 × 2 = 10 bars × 4.80 m = 48.00 m; 48.00 × 0.888 = 42.62 kg
- Mark 03 (links): 5 × 25 = 125 links × 1.20 m = 150.00 m; 150.00 × 0.395 = 59.25 kg
- Total: 113.69 + 42.62 + 59.25 = 215.56 kg, or about 0.22 t
Step by step: writing a BBS
- Give every different bar in each member its own bar mark.
- Note the diameter, grade, shape code and dimensions A, B, C from the drawing.
- Work out the cut length with the formula for that shape code.
- Multiply members × bars per member × cut length, then by the mass per metre.
- Have a second person check marks, numbers and lengths before cutting.
Common mistakes
- Using the drawing length instead of the cut length.
- Mixing shape codes from different standards in one schedule.
- Forgetting laps and starter bars.
- Counting links for one beam but not multiplying by the number of beams.
- Rounding the mass per metre too early in long schedules.
Related terms
- Engineering and constructionGlossary term
Concrete
Concrete is a building material made by mixing cement, water, sand and gravel or crushed stone. The cement and water form a paste that coats the stones and, through a chemical reaction called hydration, hardens into a strong, rock-like mass.2 min read · Added 20 Nov 2026 - Construction and QSGlossary term
Concrete volume (cubic metre)
Concrete volume is the space a concrete element fills, measured in cubic metres (m³). For a simple shape it is length × width × thickness (or depth). Concrete is priced and ordered by the cubic metre.2 min read · Added 20 Nov 2026 - Construction and QSGlossary term
Quantity takeoff (QTO)
Quantity takeoff (QTO, also "taking off") is the process of measuring quantities, such as areas, lengths, volumes and counts, from drawings, models and specifications, mainly to work out construction cost. The word "takeoff" is also used for the list of quantities the process produces.2 min read · Added 20 Nov 2026 - Construction and QSGlossary term
Bill of Quantities (BOQ)
A Bill of Quantities (BOQ) is a document that lists every item of work in a construction project with a description, a unit and a measured quantity. Contractors price each line, so every bidder prices exactly the same work.2 min read · Added 20 Nov 2026 - Construction and QSGlossary term
Method of measurement
A method of measurement is a published set of rules for how construction work is measured and described in a BOQ, so that everyone measures the same work in the same way and prices are comparable.2 min read · Added 20 Nov 2026
Frequently asked questions
Who prepares the BBS?
Usually the structural engineer, detailer or contractor's QS from the reinforcement drawings, and it is checked before bending.
Why is the BBS in kilograms?
Reinforcement is bought and usually billed by weight, so lengths are converted to mass.
Is the d² ÷ 162 rule exact?
It is a close rounding of the exact formula based on 7,850 kg/m³; product standards list the nominal mass per metre for each size.