What is Renovation? Meaning, Example and Renovation vs Refurbishment vs Retrofit

By , Founder of ZYSNOR · Updated · Checked · 5 min read

In simple words

Renovation is the work of returning an old, damaged or worn building to a good state of repair, and often modernising it at the same time, for example new finishes, repaired walls and roofs, or updated services.

Renovation differs from new building because the starting point is an existing structure, with its own condition, hidden defects and services. Most of the risk in a renovation comes from what cannot be seen until work begins.

Renovation and related words

Table of renovation, refurbishment, retrofit, restoration and maintenance with examples
One project can include renovation, refurbishment and retrofit together.

Cosmetic and structural

Renovation work is usually grouped as cosmetic (finishes, paint, tiles, fittings) or structural (walls, slabs, beams, roofs). Structural work needs an engineer's design and usually approval from the local authority; cosmetic work often does not, but rules differ from place to place.

Stages of a renovation

Five stages: survey, scope, approvals, strip out, build
The survey decides the quantities; skipping it is the costliest mistake.
  1. Survey: measure the existing building and record its condition, including damp, cracks and services.
  2. Scope: decide what will be repaired, replaced or added; produce drawings and a priced BOQ.
  3. Approvals: obtain permits where the work needs them.
  4. Strip out: remove old finishes and fittings; hidden problems often appear now.
  5. Build: repairs, new services, then finishes, with a contingency for surprises.

Worked example: re-plastering four rooms

The survey gives a total wall area of 180 m² after opening deductions. A 5% allowance for waste is added when ordering (an example figure).

  • Allowance: 180 × 0.05 = 9 m²
  • Plaster to order: 180 + 9 = 189 m²
  • The BOQ quantity stays 180 m²; the allowance is for ordering, not for measurement.
Bar chart: net wall area 180 m², waste allowance 9 m², plaster to order 189 m²
Measure net for the BOQ; add the waste allowance only when ordering.

Old plaster must also come off first, so the BOQ needs a separate item for hacking off and removing the existing finish over the same 180 m².

Why measurement matters

Renovation quantities come from the existing building, not from new drawings. An accurate survey, drawn in CAD or modelled in BIM, avoids surprises in the price and gives a base for variations when hidden defects appear.

Common mistakes

  • Pricing without a site survey.
  • Forgetting demolition, removal and disposal of old finishes.
  • No contingency for hidden defects found during strip-out.
  • Assuming renovation needs no permit; check the local rules.
  • Confusing renovation with restoration on historic buildings, where different rules may apply.

Related terms

Frequently asked questions

Is renovation the same as refurbishment?

They are often used as if they were, but refurbishment means improving by cleaning, decorating and re-equipping, while renovation means bringing back to good repair.

What is a "major renovation"?

In England's Approved Document L, it is a renovation where more than 25% of the surface area of the building envelope is renovated; other countries use their own definitions.