What is the Saudi Building Code (SBC)? Meaning, Example and How It Works

By , Founder of ZYSNOR · Updated · Checked · 5 min read

In simple words

The Saudi Building Code (SBC) is the set of building and construction requirements used in Saudi Arabia to protect public health and safety. It covers the design, construction, operation, maintenance and modification of buildings. Architects, engineers and contractors working in Saudi Arabia design and build to it.

Why it matters

Fire separation, structural sizes, insulation and other code requirements change what is drawn, and therefore what is measured and priced. A quantity surveyor needs to know which parts and which edition the design follows, or the BOQ may miss required work.

How it came about

The code is based on the International Codes and was brought into force in stages.

Timeline from the National Committee in 2001 to the 2024 edition, mandatory from 30 June 2025
The committee issues and updates the code; the 2024 edition replaced the 2018 one.
  • 2001: the National Committee for the Saudi Building Code was formed by Council of Ministers resolution.
  • 2002: the committee chose the ICC International Codes as the basis, with IEC standards for electrical work.
  • 2017: the Law on Implementation of the Saudi Building Code was issued (Royal Decree No. M/43).
  • 2018: an edition revised on the basis of the 2015 International Codes; the law came into effect, and enforcement was rolled out in stages until 2023.
  • 2024: the committee issued the SBC 2024 edition to replace the 2018 one. It became mandatory on 30 June 2025, after a 180-day transition in which the 2018 code still applied.

The 2024 edition also added new codes, including a seismic design code for steel, a code for repairing existing concrete structures and a code for concrete reinforced with glass-fibre (GFRP) bars.

Where it applies

The law applies the code to all construction works in the public and private sectors. Existing buildings come under it when they are restored, change use, are extended or are modified. The law also says the code is updated and reissued every five years.

Who looks after it

The National Committee for the Saudi Building Code issues and updates the code. It is chaired by the Governor of the Saudi Standards, Metrology and Quality Organization (SASO), with a general secretariat at SASO. Its members include the Ministry of Municipalities and Housing, the Ministry of Energy, the Saudi Council of Engineers and other government bodies.

Types

The code is split into numbered parts; the project documents name the parts and the edition that apply.

  • SBC 201: the general building code.
  • SBC 301 to 306: structural requirements, from loads to concrete, steel and masonry.
  • SBC 601 and 602: energy conservation.
  • SBC 801: the fire code.
  • SBC 1101 and 1102: residential buildings.
Table of SBC 201, SBC 301 to 306, SBC 601 and 602, SBC 801 and SBC 1101 and 1102
Each part has a number; the project documents name the parts and edition that apply.

Worked example

Does the code apply? Four projects in Riyadh:

  • A new private villa: yes, because the code covers private construction.
  • A new government school: yes, because public sector works are included.
  • An old shop converted into a clinic: yes, because this is a change of use.
  • An existing flat where no work is done: no new compliance check is triggered.
Table of four cases: new villa, government school, shop turned into a clinic, existing flat with no work
A change of use brings an existing building under the code.

Common mistakes

  • Designing to the 2018 edition after the 2024 edition became mandatory.
  • Assuming a code from another country applies unchanged because the SBC is based on it.
  • Forgetting that existing buildings must comply when they are modified or change use.
  • Checking only SBC 201 when the fire, energy or structural parts also apply.

Related terms

Frequently asked questions

Does the SBC apply to private villas?

The law covers construction works in both the public and private sectors.

How often is it updated?

The law says every five years.

Which edition applies now?

The SBC 2024 edition, mandatory since 30 June 2025. The project documents should name the edition and parts used.